This article
originally appeared in the September 2002 edition of Railway Bylines
(Vol.7 No.10) and is reproduced here with the permission of the author
and publisher. Railway Bylines is published monthly by Irwell Press, 59a
High Street, Clophill, Beds MK45 4BE. You can find out more
about Railway Bylines magazine at the publisher's website:
www.irwellpress.co.uk
|
|
Seaham Harbour and its railways
by Steven Oakden
Railway
picture Gallery |
Seaham Harbour, roughly midway between Sunderland and Hartlepool on
the County Durham coast, had one of the best-known and best-loved
industrial railway systems in the country. This celebrity status was
wholly justified, not least of all because the system was home to a
marvellous array of locomotives ranging from ex-‘main line’ tender
engines to primitive vertical-boiler types. There was also vintage
rolling stock – chaldron wagons were still in use in the 1970s. On top
of all that, the system as a whole boasted a fascinating network of
lines including much that was highly photogenic and wonderfully
atmospheric.
The history of Seaham Harbour is very complex but, as it has been
discussed in varying depths elsewhere, for the purposes of this
article we will concentrate mainly on the working of the harbour
railways. That said, a very brief potted history is in order, if only
to explain the function of the harbour.
Background
Seaham Harbour was constructed by the 3rd Marquis of Londonderry
as an outlet for the coal from his collieries, the original dock (the
North Dock) opening to commercial shipping in July 1831. From the
outset there was a rope-worked waggonway to convey coal from
Londonderry Colliery at Pittington to the dock. As the local mining
industry developed Seaham Harbour was extended and improved to keep up
with the demand. A second dock – South Dock – was partly opened in
July 1835, and there were further substantial extensions in 1902-05
and again in 1927/28.
An unmistakable feature of the harbour was the massive shipping
staiths at the South Dock. Ultimately there were five such staiths:
North Berth, Middle Berth, Pole Berth and Castlereagh Berth (all along
the west side of the dock) plus the New Berth on the east side of the
dock extension. Castlreagh Berth and New Berth were built of concrete
with timber decking and top work whereas the other, older, staiths
were timber set into concrete. Despite the decking timbers being 3"
thick, they were not immune to rot. Indeed, it was not unknown for an
unwitting member of the railway staff to find one of his feet going
right through them!
On the corporate front, in 1899/1900 the 6th Marquis of Londonderry
reorganised his industrial interests. His public railway (the
Londonderry Railway, the main line of which extended from Seaham to
Sunderland) was sold to the North Eastern Railway, his collieries were
vested in the newly-formed Londonderry Collieries Ltd, and the Seaham
Harbour Dock Company Ltd was formed to administer Seaham Harbour. Four
of the locomotives which had been part of the sizeable Londonderry
fleet were transferred to the Seaham Harbour Dock Company.
By the early 1930s some 2¼ million tons of coal was being exported
through Seaham Harbour annually. Some of it came from two of the local
Londonderry-owned collieries – Seaham Colliery (connected to the
harbour by a self-acting incline) and Dawdon Colliery (connected by a
¾ mile long branch) – but some also came by rail from South Hetton
Colliery and Murton Colliery, both of which were owned by the South
Hetton Coal Company.
That is how things remained until the National Coal Board came into
being on 1 January 1947. The NCB took over the collieries and the
railways which connected them to Seaham Harbour, but the harbour
itself remained under Seaham Harbour Dock Company control. By this
time it had a fleet of about a dozen locomotives.
The harbour railways
The harbour railways were divided into two main sections. The
majority of the traffic was worked on the high level section which ran
along a shelf on the cliff above the South Dock and extended
southwards past the harbour along the coast to Nose’s Point (where
ballast or spoil was taken for tipping into the sea). The high level
section included the lines serving the shipping staiths. Railway
wagons loaded with coal were run out on the staiths and the coal was
tipped through the bottom doors of the wagons, via shutes, into the
ships waiting below. After discharging, the empty wagons ran forwards,
then ran back down a gradient into a hollow (invariably referred to as
a ‘hole’). When a number of empties were ready they were collected by
a locomotive and taken back to one of the inclines or to Dawdon
Colliery or the LNER/BR exchange sidings near Dawdon Colliery.
On the low level section, some of the lines weaved along the quayside
beneath the staiths. Their main functions were to enable coal which
had been spilt from the staiths to be collected and, as there was no
road access to the quays directly beneath the staiths, to deliver
stores to ships. The low level lines also extended on to the
breakwaters and were used to transport equipment and materials when
the breakwaters required repairing.
The line connecting the low level to the high level was known as the
‘Dogger Bank’. It was a ferociously steep climb which, it is reckoned,
was around the 1 in 11 mark. It is certainly the steepest bit of
adhesion-worked line this writer has ever seen. Matters were not
helped by the grass growing on the track and the fact that the line
was accessed at the bottom by a short headshunt. There was no run-up
here – the driver had to give an engine lots of steam, and hope! It
was exciting to see this line in use as it ran along a ledge on the
cliff face with a high retaining wall on the west side and an almost
sheer drop on the other. More of this anon…
Locomotives
The Seaham Harbour Dock Company’s locomotive fleet included a
number of veterans, several of which had interesting pedigrees. One of
the most interesting of the early engines was No.1 SEATON. At the time
the NER took over the Londonderry Railway in 1900, an 0 4 4T was under
construction at the Seaham Engine Works (part of the Londonderry
empire). This engine had originally been intended for passenger duties
on the Londonderry Railway but, as the NER had ample passenger engines
of its own and as there was no requirement for passenger engines on
the Seaham Harbour railway system, the unfinished engine was taken to
the Seaham Harbour Company’s new workshops to be completed as an 0 6
0T instead. When it eventually entered service, it was designated No.1
SEATON and had a works plate inscribed ‘Seaham Harbour Engine Works
1902’.
SEATON was kept in regular use at Seaham. Its 4ft 6in wheels meant
that it was sluggish when pulling away but, once it got going, it was
fast. Former Seaham Harbour Company driver Jimmy Taylor recalls that
it was not a popular engine to work with – this was largely on account
of its coil springs which made the ride somewhat lively. Jimmy also
recalls that the engine was fitted with new cylinders, but these were
smaller than the original ones and the engine was never as good
afterwards. Previously it could get 20 empties out of one of the
‘holes’, but with the smaller cylinders it could manage only ten at a
time. It was therefore necessary to make two trips to clear one of the
‘holes’ before a rake of twenty wagons could be assembled for
forwarding to the south end sidings.
The harbour company also had four locomotives which were purchased
from the North Eastern Railway. Among them was a tender engine named
CLIO which had been built by the NER at Gateshead Works in 1875 and
had been purchased in 1911. It was not altogether ideal for work at
Seaham, its comparatively large wheels being unsuited to frequent
starts on steep gradients with heavy trains; furthermore, the overall
length of the engine and tender were troublesome when passing through
sets of points. Surprisingly, though, there was little problem with
the six-wheel tender derailing on the rough tracks. CLIO lay
dismantled for many years finally being scrapped in 1955. Its tender
was retained and used to transport water for cement making.
MARS and MILO were two other ex-NER engines. They were old Robert
Stephenson 0 6 0STs of 1875 vintage but, despite their age, were well
regarded and were used on the North Berth. They mainly handled
chaldron wagons which came down the Seaham Colliery incline. The
chaldron wagons (more of which anon) were retained for this duty on
account of the low bridge at the foot of the incline.
Despite the small size of the chaldron wagons, the comparatively
sturdy MARS and MILO often had difficulties getting sixteen or so of
them out of ‘the hole’ at North Berth if the rails were greasy.
Shunter Gordon Davison remembers having to get off the footplate and
use a spanner to knock the sand pipes to try and get a flow of sand to
the rails. On MARS and MILO this was a dangerous job as the sand pipes
were behind the buffer beam under the overhang of the running board.
Gordon learned of the dangers the hard way – on one occasion the end
of the coupling rod hit him on the head and knocked him out.
Fortunately, he fell backwards.
Former driver Jimmy Taylor remarks that the two saddle tanks had good
enclosed cabs. This was in marked contrast to 0 6 0 tender engine CLIO
which had a very spartan cab which offered scant protection against
the elements.
There were also two Peckett 0 6 0STs which had been purchased new in
1905/06. Named SEAHAM and SILKSWORTH, they were not identical – the
former was one of the maker’s ‘B2’ class with 14in cylinders whereas
the latter was an ‘F’ class with 15in cylinders. The two Pecketts saw
a lot of use but they were not held in particularly high regard as
they were not as strong as some of the other engines. Although
SILKSWORTH (which was known to the crews as ‘The Clogger’) was a good
steamer, it could manage only eleven empties out of the holes. SEAHAM,
on the other hand, was a poor steamer. It was generally considered
that the deep firebox was a cause of over-firing – if too much coal
were added it restricted the air flow through the fire. SEAHAM once
shed one of its tyres and the rods were consequently removed. It ran
for a while in this condition and, not altogether surprisingly, the
adhesion was utterly hopeless. Jimmy Taylor referred to the Pecketts
as ‘numb’ engines because they weren’t flexible to operate. A driver
had to be careful with them to get the work done – it wasn’t just a
case of throwing the fire on.
Among the other engines employed at Seaham was DICK, a small Hunslet 0
4 0ST which was used mainly on ballast work and for taking stores to
ships in the dock.
In the opinion of the Seaham crews, the best engines the company owned
were Hawthorn Leslie 0 6 0STs JUNO and NEPTUNE. These engines were
powerful and were good riders. The two were not identical – NEPTUNE
had smaller wheels and a higher boiler pressure. Of the two engines,
the crews favoured JUNO. Jimmy Taylor confirmed that JUNO was a good
steamer – with a load of empties up out of the ‘holes’ the injector
had to be put on to prevent the boiler blowing off whereas, on the
same work, NEPTUNE’s boiler pressure would drop. JUNO often worked at
the south end of the harbour. Three engines were usually employed
there.
The ‘coffeepots’
At Seaham, the age-old railway soubriquet of ‘coffepot’ was
applied to two vertical-boilered locomotives (Nos.16 and 17) which had
been built in the early 1870s by Head Wrightson of Stockton-on-Tees
and the famous old Lewin 0 4 0 tank engine, No.18. These three
locomotives looked after the work on the low level lines around the
bottom of the staiths; they were the most suitable engines for that
work on account of their small dimensions – some of the lines,
particularly through the tunnels and under the staiths, had very
limited clearances, and there were also some very tight curves which
were too sharp even for ordinary 0 4 0STs .
The Head Wrightson locomotives were extremely basic machines. They had
no cab so the driver had to stand on the framing and simply get on
with it. One of the Seaham pair, No.16, had vertical cylinders and was
geared but the other, No.17, worked in a more conventional manner. The
gearing of No.16 sometimes proved troublesome – the cogs were mounted
under the framing and therefore received a liberal helping of muck,
while debris left between the rails presented another sort of problem.
Although No.16 was the better steamer, No.17 was the more powerful. If
a driver had steaming problems with one of these engines the procedure
was to lift the cover off the top of the boiler and clean the tubes.
However, this usually resulted in the loosened soot being thrown all
over the driver.
The Lewin (No.18) was, arguably, the most famous of all the Seaham
locomotives. Built in 1877 (or so it is believed) as an 0 4 0 well
tank, it had been twice rebuilt in the Seaham Dock Company’s
workshops, firstly as a side tank and, in 1927, as a saddle tank. It
was a remarkable veteran which positively oozed character. One of the
former Seaham drivers, Hal Weetman, recalled the day when it suffered
a bent coupling rod, the result of an altercation with some rocks on
the beach. The rod was removed and taken to the workshops to be
straightened, but this left the engine stranded on the beach (to the
north of North Dock) and uncomfortably low on water. The only solution
was to fill up with seawater until the repaired rod was brought back
for fitting. The seawater might have been a quick solution, but it did
little for the Lewin – the engine primed terribly.
The Lewin was regarded by the crews as a good little engine. It seemed
to be going on forever – by the mid-1960s it usually worked the
morning shift and finished about noon – but it finally succumbed in
the early 1970s. Hal Weetman was working it at the time. There was
steam blowing from the flange around the dome and Hal took the engine
to the fitting shed where it was condemned on the spot. Thereafter
lorries and dumper trucks took over the work.
The Lewin had gained the status of the oldest active steam locomotive
in the country. After ceasing work it was laid aside at Seaham but in
January 1975 it was taken to Beamish Museum for preservation. It was
restored to its original condition with a well tank and no cab and,
although it now looks very smart, there was a strong feeling among the
Seaham crews at the time that it should have been preserved in its
latter-day condition.
On the whole, the duties of the ‘coffeepots’ were fairly light. When
not on ‘coal clearance’ work under the staiths the engines trundled
around the low level lines with perhaps a couple of flat wagons, one
loaded with cement and the other with a cement mixer. They would take
the equipment to wherever maintenance work – repairing cracks in the
harbour walls, for example – was being undertaken. In winter, damage
to the breakwater and sea walls was common.
As for the repair work itself, the concrete was mixed on site at a
depot near the low level engine shed. The engines were used to bring
in wagons containing the cement (in bags) and also to take the
finished blocks of concrete on flat wagons for storage. The sand,
incidentally, was obtained from the beach to the north of the harbour
and, as well as being used for block-making, it was also used for the
engines sandboxes and for building work on the upper levels. The
engines were also used for shunting the 5 ton cranes which were used
to lift the concrete blocks.
Valve trouble
As on almost all railway systems everywhere, the engine crews
sometimes resorted to unofficial methods to keep their charges
working. At Seaham, the Head Wrightson locomotives came in for such
treatment. The men used to weight the engines’ safety valves either by
holding on to them or, as increasingly became the practice, by placing
a chain on the safety valve lever. In the case of No.16 this was not
to get extra pressure, but because of a fault with the safety valves –
they hadn’t been properly ground into the casting so steam continually
by-passed them. No.16 ran around with the chain permanently on the
valve lever as, otherwise, there simply wasn’t enough pressure for the
engine to do any work. Jimmy Taylor reported this to the foreman
fitter, but nothing was done to repair the fault.
Although the weighting down of the valves was common practice and was
known to the management, it was quite unofficial. Indeed, on one
occasion Jimmy Taylor was suspended for several months for having
resorted to the practice despite the fact that, when his boss was
riding on the footplate, he would hold the safety valves down for
Jimmy as the driving position was on the other side of the footplate
to the safety valve lever!
Nevertheless, the vertical-boiler engines carried on having their
safety valves held down until the end of their days. The Lewin (No.18)
escaped such treatment as its safety valves couldn’t be weighted.
An accident
Jimmy Taylor recalls one tragic incident which took place in about
1946. He was driving ‘coffeepot’ No.16 which had taken the 5 ton crane
out to the south breakwater where repair work was needed. In the
customary manner, the crane driver was accompanied by a ‘crane lad’
who, besides helping, was learning how to operate the crane. While the
work was in progress Jimmy had to take No.16 to the high level to get
lubricating oils and hand cleaning aids, leaving the ‘crane lad’
driving the crane which was pulling a flat truck loaded with blocks.
The crane toppled over the wall on to the beach, taking the flat wagon
with it. The blowdown valve of the crane was knocked off and allowed
steam to rapidly escape from the boiler – the crane driver was very
badly scalded. The ‘crane lad’ also went over the wall – he was
trapped under the boiler and the driver, despite his own appalling
scalds, told the first men on the scene to “see to the bairn”.
Unfortunately, the ‘crane lad’ was dead. The driver himself died of
his injuries a couple of days later. There was a third casualty – a
workman had been standing on the wagon attaching the blocks on to the
crane hook went over the wall as well. He was badly injured.
Sentinels
In the autumn of 1956 the Seaham Harbour company had a
two-year-old 200hp Sentinel on trial. It would seem that the
management was impressed as the company soon purchased the locomotive.
Two similar Sentinels were purchased new in 1956/57. However, even if
the management had been optimistic about the locomotives, the crews
were distinctly unimpressed. The locomotives might have had adequate
power for ordinary requirements, but for the type of work they had to
undertake at Seaham they were short on adhesive weight and they were
particularly unsuited to the gradients. Jimmy Taylor recalls that a
lot of trouble was experienced with the boilers – they would sometimes
become red hot and would start to bulge under the high pressure of
225lbs. Jimmy opines that the water space was not large enough and
that, on the gradients and undulating track, the top of the boiler
would be uncovered. This meant that the red hot plates were constantly
been covered and uncovered by water. Some of the shunts required
sudden bursts of power followed by coasting down hill – this did the
engines no good at all. Indeed, when a visiting insurance inspector
saw the boiler plates glowing a dull red and bulging he stopped the
locomotives from being used.
As will be seen in the accompanying summary of locomotives, one of the
Sentinels was returned to the maker in 1958 and, the following year,
another went to Thomas Hill where its frame and wheels were reused for
its ‘conversion’ to a 4 wheeled diesel-hydraulic.
1960s acquisitions
As the years progressed an increasing amount of Seaham’s
rail-borne traffic was handled in larger steel-bodied wagons, and many
of the smaller and older Seaham locomotives with lower boiler
pressures were found wanting. To keep up with traffic requirements the
harbour company looked to the second-hand market and, between 1960 and
1963, purchased no less than seventeen steamers from other local
industrial concerns. These proved to be a mixed bag: some were good
but others were clapped out.
At the ‘more useful’ end of the scale were five Hawthorn Leslie 0 4
0STs purchased from the Consett Iron Company in 1960. Four of these
had 16in cylinders and proved to be good, powerful engines which were
capable of lifting up to twenty empties at a time out of the ‘holes’.
Despite the engines’ usefulness, the crews reckoned that they weren’t
as comfortable to work on as JUNO and NEPTUNE. The other Hawthorn
Leslie purchased from Consett was a smaller 14in example. It, too,
proved to be a useful acquisition – at least, it was until it was
converted to oil-firing in the early 1960s. As an oil-burner it gave a
lot of trouble with fuel leaks on the footplate and fumes. There were
also complaints about the noise made by its burners.
Two other second-hand Hawthorn Leslie 0 4 0STs came from the South
Durham Steel & Iron Company’s works at West Hartlepool. These bore
Nos.1 and 3. None of the Seaham men this author has spoken to
remembers No.1 working, but it is known that No.3 did work at Seaham.
Dorman Long was the source of eight very squat but very large 0 4 0STs
– four came from DL’s Acklam Works and four from Britannia Works, both
premises being in Middlesbrough. These engines might have been
satisfactory on the flat, moving slowly with heavy loads, but they
were no good charging steep gradients at Seaham. They were poor
steamers – heavy loads could often be moved only a few hundred yards
before steam ran out. It is believed that only some of the eight were
ever put to work at Seaham, the others being merely a source of
spares. The crews were distinctly unimpressed with these engines,
especially the very cramped cabs.
The largest second-hand acquisition of the period was Manning Wardle 0
6 0T No.44. This engine had started life as a saddle tank but had been
substantially rebuilt and fitted with side tanks at the NCB’s Lambton
Engine Works in 1951. With its narrow cab, high dome and big tanks it
was an aesthetic disaster. The Seaham Harbour company purchased it
from the NCB in February 1960, it having latterly been based at
Philadelphia for use on the old Lambton Hetton & Joicey system.
Opinions differ about this engine. Some of the older Seaham drivers
liked it but some other drivers reckoned it was a big clumsy lump. The
shunters didn’t like the height off the ground – if they missed their
footing it was a fair way down.
Diesels
As can be seen from the accompanying table, five English Electric
305hp diesel-hydraulics were purchased new in 1967. Before long they
were painted light blue with yellow cabs. They might have looked
fairly dainty but, in practice, they were very powerful and efficient.
The diesels were housed in a lengthy single-road shed; this was
something the steamers had never experienced – the old steam ‘shed’
had had walls and window frames, but no roof.
The diesels displaced the steamers and, with one exception, the
remaining steamers were scrapped en masse during 1967. The exception
was the little Lewin which was retained to handle the breakwater
repair trains. As noted earlier, it finally ceased work in the early
1970s.
Chaldron wagons
A familiar feature of the Seaham Harbour railway scene was the
chaldron wagons, invariably known at Seaham as ‘black wagons’. They
had bottom-emptying doors suitable for discharging their loads at
riverside staiths. They had been widely used for coal traffic since
the days of the early waggonways, and until the early 1900s were also
used by the ‘main line’ railway companies.
On the Seaham system the standard chaldron had a tare weight of about
2½ tons and a capacity of four tons. Some of the Seaham chaldrons
remained in use until the 1970s – it is thought that they were the
very last in regular use anywhere in the country – though latterly
they were used mainly as mobile rubbish skips.
That said, until the 1960s the chaldrons were also used for coal
collection. To explain… With such huge quantities of coal being
shipped – even in the 1960s almost 1,500,000 tons was exported through
Seaham annually – there was inevitably some spillage. This was
collected from beneath the staiths and loaded into chauldron wagons.
Being small, they could be loaded by shovel.
Staffing
In the 1950s and ‘60s seven engines were in use each day. Six of
these were out on two shifts: 6am-2pm and 2-10 p.m. The late shift
often stayed on until midnight if work demanded, for example to finish
loading a ship so that it could make the tide. Also, at least one
engine usually worked until midnight on spoil tipping duties. The
seventh engine in steam each day worked the low level lines around the
bottom of the staiths.
The Seaham crews tended to work on a six-week cycle with two weeks on
each job; so it would be two weeks on the North End, two on the South
End then two on the Low Level lines. The men driving the ‘coffeepots’
were often firemen on the top lines – the ‘coffeepots’ were suitable
for the less experienced because of the light duties they performed.
As well as the engine crews there were two sets of platelayers with 8
to 10 men in each gang. All told, in the 1960s the dock company
employed 340 men including engineers, coal trimmers, tug and dredger
crews, administrative staff etc.
‘Dogger Bank’
Various mentions have been made of the ferociously-graded ‘Dogger
Bank’ – the connecting line between the low level and the high level
systems. Sanding was very important while working the Dogger Bank.
Besides having sand in the engine’s sandboxes, an old 5 gallon drum
was carried which also contained sand. In difficult conditions a
shunter could grab a handful of sand from the drum, jump off the
engine and get the sand on to the rails.
Before taking cranes down the bank it was good practice for an engine
to go down light engine and apply sand to the rails, then come back up
to collect its train. If the rails were really bad a sprag was pushed
into the wheels of the wagons to lock them; this was a sensible safety
precaution as the ‘black wagons’ had rather inefficient brakes while
the flat wagons had none at all. On one occasion Hawthorn Leslie No.10
was making its way up the bank pushing a couple of ‘black wagons’ when
a tube burst. This put out the fire and the boiler pressure plummeted,
rendering the engine useless until repaired. JUNO went down and pulled
the trucks and loco up.
On another occasion SILKSWORTH had just negotiated the worst of the
climb when the coupling to the first wagon broke. Three wagons
carrying sand, cement, a cement mixer and other equipment went
hurtling down the bank to land up in wild abandon at the bottom with
wood, sand and bits of equipment everywhere. The crews found that the
best engines on the Dogger Bank were JUNO or NEPTUNE which could get
five or six Black Wagons of spillage up the bank.
Although the railway work at the low level usually fell to the
‘coffeepots’, if anything more than a couple of empty flat wagons
needed to be taken up the Dogger Bank this was beyond the engines’
capabilities so the wagons were left in the headshunt to be collected
later by a larger engine. The Lewin (No.18) exhibited a waggling gait
when working the Dogger Bank. Hunslet 0 4 0ST DICK used to display a
different phenomenon when on the bank – despite having a long, narrow
chimney the exhaust would go, not straight up in the air, but to the
sides. Even more curious was that three puffs would go to the right
and the next would go to the left!
|
Reports of visits to Seaham Harbour
occasionally appeared in the railway press.
These two featured in
the Railway Observer.
10 August 1955: ‘Ex-North Eastern Railway 0 6 0ST Mars was noted
shunting colliery tubs on the harbour lines. It works a double
shift, a day of sixteen hours. In comparison with similar engines
at Backworth Colliery, Mars appears to be in its original
condition with Salter safety valves and an old type cab, while the
name Mars is in bold letters on an oval nameplate similar to the
old NER numberplate and in the same position as the latter on the
cab sheets’. (A subsequent report added that the nameplate of Mars
– and also that of Milo – were in fact the old NER numberplates
with the numerals removed and the letters substituted.)
28 December 1966: ‘The following were noted at the company’s shed:
Nos.3, 10, 18, 38, 173, 177, 183. There were two further 0 6 0STs
and an 0 4 0 lying out of use but unidentifiable. The interesting
0 4 0ST, No.18, built by Lewin of Poole, was also out of use. Most
of the remaining locomotives in steam were in deplorable external
condition. Work was in hand on diesel stabling facilities and one
diesel shunter was noted working at the docks…’
|
Maintenance
The loco water at Seaham was very hard so good washouts were
imperative. Tablets were added to the water to try and alleviate the
problems, but this was not a long-term solution. Indeed, on one
occasion No.38 suffered a bulge in the side of its firebox; usually, a
patch would have put over the bad area once it had been re-stayed, but
the boilersmiths let in a new patch having cut out the overheated
section and welded the patch and fixed new stays. The workmanship was
first class. The engine was also overhauled with a new pumped oil
supply to all the axleboxes, cylinders, slide bars and valve chests.
It ran superbly. Other engines were similarly equipped when they were
overhauled.
The locomotive maintenance staff were always held in high regard by
the crews, but towards the end of steam working at Seaham a corporate
reluctance to spend money on soon-to-be-replaced equipment meant that
the engines became very run down. Steam and water leaks in boilers
were becoming endemic. When an engine started popping tubes or the
ferrules on the tubes needed replacing, the job was hampered by the
arch in the firebox; sometimes, the boilermen’s solution to this
problem was to knock out the arch. However, the brick arch had been
there for a purpose – it not only caused better combustion and greater
efficiency in the amount of coal used, but it also protected the tube
ends. Furthermore, the heat it retained caused slower cooling of the
firebox when the engine had its fire thrown out at the end of a day’s
work. The removal of the arch might have solved one problem but it
created others – for example, JUNO and NEPTUNE both suffered cracks in
the top corners of the firebox. The crews were trying to work a heavy
shift with copious amounts of water running into fireboxes. Keeping
steam and water levels up in such circumstances was very difficult.
From the crews’ point of view, the arrival of the diesels came as a
blessed relief.
Decline
Throughout its long life Seaham Harbour had relied almost
exclusively on only one commodity – coal. That situation proved to be
the port’s downfall as, when the coal industry started to decline, so
did the harbour. Another factor working against Seaham was that the
largest ships it could accommodate were a fairly modest 4,500 tons
deadweight. Other ports in the north-east – Sunderland, Newcastle and
Blyth – could handle much larger vessels. Indeed, the CEGB had
invested in new ‘super colliers’ that were up to the maximum size that
could be handled at Sunderland and at Harton Staiths on the Tyne, and
it became the usual practice for coal from the collieries at Seaham to
be taken by MGR train to the Tyne for shipment.
In 1978 the NCB ceased using Seaham for shipping coal and the staiths
were soon demolished, thereby dramatically changing the appearance of
the harbour. But despite the loss of the coal traffic the harbour
company – to their credit in difficult trading circumstances –
succeeded in attracting some new trade: steel came for export and
there were even some imports. However, with the exception of the
steel, all the newfound traffic was moved by road, so the harbour
railway system saw less and less usage.
By the 1980s the principal traffic handled at the harbour was stone or
colliery waste. Mechanisation of coal cutting produced huge quantities
of stone and, at one time, Dawdon, Vane Tempest, South Hetton and
Murton collieries all disposed of their spoil at Seaham. There was
also the steel traffic (mainly from BSC Teesside), though from the
railway’s point of view this offered only occasional activity. Wagons
of steel arriving for export were accepted at Seabanks signal box and
moved by the diesels to the dock company offices. Here the steel was
loaded on to lorries to move it down to the berths for loading. When a
steel shipment came, four of the five diesels might be in use; at
other times three sufficed – two at the Dawdon end and one to and from
the incline to Seaham Colliery.
During the 1980s and 1990s the local mining industry contracted. In
February 1982 Vane Tempest and Seaham collieries merged, with Seaham
becoming the coal winding and washing plant. Traffic from South Hetton
Colliery ceased in 1984, the incline from Seaham Colliery to the
harbour closed on 17 July 1987 (when BR took over responsibility for
coal and spoil traffic), Dawdon Colliery closed in July 1991, and the
‘combined’ Seaham and Vane Tempest collieries were mothballed on 23
October 1992. They were officially closed in May 1993.
Although Seaham Harbour no longer handled coal exports, the
contraction of the local mining industry nevertheless had a knock-on
effect at the harbour. This meant that the fleet of five diesels was
over-large, so one of the five was scrapped in 1988 and two were sold
in 1989. The other two diesels (D4 and D5) remained on site for the
steel traffic, but that traffic ceased in 1992 and the two locomotives
were mothballed in the vain hope that they would be needed in the
future. That did not happen, and in 1994 they were sold to the scrap
merchants C.F.Booth of Rotherham.
Seaham Harbour is still in commercial use today; imports include
forest products, fertiliser, steel and sand, and exports include
limestone and wood chips. The harbour has modern container handling
and bulk loading facilities, but none of the traffic arrives or
departs by rail.
|
Contributor’s note: I would like to thank
Stan Rogers, Gordon Davidson, Jimmy Taylor, Jimmy Price, Hal Weetman,
Eddie Mayhew and Roy Hanson for their help with the preparation of
this article. Reference was also made to Industrial Locomotives of
Durham (Industrial Railway Society, 1977), Steam Railways in Industry
by H.Gamble & C.T.Gifford (Batsford, 1976) and Industrial Railways of
Seaham by A.J.Booth (Industrial Railway Society, 1994). Thanks also to
Colin Mountford for locomotive information.
|
SEAHAM
HARBOUR DOCK COMPANY – summary of locomotives
(listed in order of acquisition)
Makers abbreviated thus:
BH
– Black Hawthorn; BT – Blyth & Tyne Railway (Percy Main Works);
EE – English Electric (Vulcan Works); HE – Hunslet
Engine Co; HW – Head Wrightson; MW – Manning Wardle;
NE – North Eastern Railway (Gateshead Works); P – Peckett &
Sons; RS – Robert Stephenson; RSH – Robert Stephenson &
Hawthorns; S – Sentinel; SH – Seaham Harbour Dock Co;
SL – Stephen Lewin; TH – Thomas Hill; TR – Thomas
Richardson; YE – Yorkshire Engine Co
|
No.
and/or
name |
Type |
Maker; W/No. |
Built |
Driving wheels |
Cylinders
or
h.p. |
Acquired |
Disposal (scrapped unless stated otherwise) |
|
16 |
0‑4‑0VBT |
HW 21 |
1870 (R) |
2' 6" |
6" x 12" (v) |
1899 ex-Londonderry |
6.1959 (P) |
|
17 |
0‑4‑0VBT |
HW 33 |
1873 (R) |
2' 5½" |
9" x 14" (o) |
1899 ex-Londonderry |
6.1962 (P) |
|
18 |
0‑4‑0WT (R) |
SL - |
1877 |
2' 6" |
9" x 18" (o) |
1899 ex-Londonderry |
1.1975 (P) |
|
3 (DAWDON) |
0-6-0 (R) |
TR 254 |
1855 (R) |
|
15" x 22" (i) |
1899 ex-Londonderry |
? |
|
1 SEATON |
0-6-0T (R) |
SH - |
1902 |
4' 6" (?) |
(i) |
New |
5.1962 |
|
19 |
0‑4‑0ST |
BH 203 |
1871 |
2' 9" |
9" x 16" (o) |
1903 ex-Painton Colliery |
3.1939 |
|
REX |
0‑4‑0ST |
MW 838 |
1885 |
3' 1" |
10" x 18" (o) |
1905 ex-Pearson (contractors) |
1939 |
|
DICK |
0‑4‑0ST |
HE 628 |
1895 |
2' 10" |
10" x 15" (o) |
1905 ex-? |
12.1963 |
|
SEAHAM |
0-6-0ST |
P 1052 |
1905 |
3' 7" |
14" x 20" (o) |
New |
1961 |
|
SILKSWORTH |
0-6-0ST |
P 1083 |
1906 |
3' 7" |
15" x 21" (o) |
New |
7.1963 |
|
MILO |
0-6-0ST |
RS 2241 |
1875 |
4' 0" |
14¾" x 22" (i) |
1907 ex-NER |
7.1963 |
|
AJAX |
0-6-0 |
BT - |
1867 |
4' 6" |
16" x 24" (i) |
1907 ex-NER |
1926 |
|
MARS |
0-6-0ST |
RS 2238 |
1875 |
4' 0" |
14¾" x 22" (i) |
1908 ex-NER |
7.1963 |
|
CLIO |
0-6-0 |
NE - |
1875 |
4' 6" |
17" x 24" (i) |
1911 ex-NER |
1955 |
|
JUNO |
0-6-0ST |
HL 3527 |
1922 |
3' 10" |
16" x 24" (o) |
New |
1.1967 |
|
NEPTUNE |
0-6-0ST |
HL 3898 |
1936 |
3' 8" |
16" x 24" (o) |
New |
1.1967 |
|
SENTINEL |
4w VBT |
S 9575 |
1954 |
3' 2" |
6¾" x 9" (v) |
1956 ex-Sentinel (demo loco) |
6.1965 |
|
TEMPEST |
4w VBT |
S 9618 |
1956 |
3' 2" |
6¾" x 9" (v) |
New |
1959 to TH* |
|
- |
4w VBT |
S 9619 |
1957 |
3' 2" |
6¾" x 9" (v) |
New |
2.1958 to Sentinel |
|
- |
0-6-0DE |
YE 2668 |
1956 |
|
400hp |
1958 on trial |
1958 ex-trial |
|
18 |
0-6-0ST |
BH 32 (R) |
1867 (R) |
4' 0" |
15" x 20" (o) |
1960 ex-NCB |
12.1963 |
|
44 |
0-6-0T |
MW 1934 |
1917 (R) |
3' 9" |
17" x 24" (o) |
1960 ex-NCB |
7.1963 |
|
No.10 |
0‑4‑0ST |
HL 3476 |
1920 |
3' 6" |
14" x 22" (o) |
1960 ex-Consett Iron Co |
12.1966 |
|
No.15 |
0‑4‑0ST |
HL 3873 |
1936 |
3' 8" |
| | |